Current update
Construction activities began on site in January 2024. The next major package of construction work, following the now complete utility works, includes:
- new southbound flyover on the Monaro Highway over Lanyon Drive (including three-metre wide sealed shoulders)
- upgrading of the highway road pavement from David Warren Road through to Sheppard Street (including three metre wide sealed shoulders)
- new widened bridge on the northbound carriageway over Dog Trap Creek just north of Lanyon Drive.
Initial works on site include significant ground clearing and earthworks with heavy machinery including excavators and trucks moving around the site.
Temporary traffic management
Reduced speed limits will be place for the duration of the work. This will generally be 60km/h on both highway carriageways while work is underway. Temporary lane closures and speed reductions to 40 km/h will intermittently be in place outside peak periods.
The changed speed limit is required for several reasons including each of the below.
- The project site is a very restricted work area due to the existing carriageway and available median and verge areas; this means works will be carried out in close proximity to the existing roadway and road users.
- Temporary concrete safety barriers adjacent to travel lanes, reduced lane and shoulder widths, and temporary traffic diversions are required to accommodate the works safely.
Whilst every effort is made to minimise disruption throughout construction, including maintaining traffic lanes where possible, there are expected to be travel time impacts during the project. We encourage everyone to think about how they travel and whether you are able to travel outside of peak periods.